Mains distribution busway




Department of Power supply of industrial enterprises

 

 

Course work

On discipline: Electric power supply

On theme: Calculation of electrical loads and making workshop networks schemes

 

 

Done by: st. of group EE-13 Sydykova N.N

№ of record book: 134140

Checked: Soltanayev A.M

«____» ___________________ 20___y.

 

Almaty, 2016

Contents

 

 

Task for coursework  
  Table 1 – Initial data for option 40  
  Table 2 - Initial data of the workshop  
  The calculation of the initial data of workshop  
  The calculation of electrical loads of workshop.  
  Calculation of lighting load of the workshop  
  Table 4 - The calculation of loads on the workshop  
  Table 5 - Technical data of electroreceivers  
  The calculation of the technical data for power consumers and the choice of protective devices  
  The choice of circuit breaker, cable and type of busways  
  Table 7 - Calculation of protective devices to ER  
  Table 8 – Calculation protective devices to DB, DBW, LL, DMBW  
  Calculation of short circuit currents  
  Calculation of resistance on the circuit area  
  Calculation of short circuit on the circuit areas  
CONCLUSION  
   

 

Task for coursework

 

 

For one of the workshops of the industrial enterprise is required to perform the following measures:

1 Mark out the supplying nodes of the electrical receivers ER (power boards, distribution busways).

2 Determine the power loads at supply nodes, lighting load and design load of whole workshop with method of utilization factor and maximum coefficient.

3 Select a scheme of supply and distribution network of workshop.

4 Select a number and capacity of transformers, place of location for workshop substation.

5 Determine a section and type of wires, cables and busbars in workshop network.

6 Choose electrical equipment and calculate currents of fuse-links and tripping setting of circuit breaker.

7 Draw a plan of electrical power network of the workshop.

8 Draw a scheme of power supply and distribution network of workshop with the indication of section of wires, cables, and parameters of shutdown and protective equipment and electrical receivers.

9 Specify parameters of the network, protection devices, the neutral wire from complete transformer substation (CTS) to the most remote powerful electric motor, design and peak currents in the designed single line scheme of supply and distribution networks up to 1 kV of the workshop.

10 Determine the three, two and single-phase short-circuit currents in the designated point K1, K2 and K3. Assume conditionally the short-circuit power at the high side of workshop transformer in the range 100¸150 MVA. Calculate twice the single-phase short circuit: at the transformer scheme D/Uо - 11 and the scheme U/Uо - 12.


Table 1 – Initial data for option 40

 

№ by plan № of task  
Name of equipment Installed power of electroreceivers (kW)
1,2 Vertical milling  
3,4,21,22,25 Chamber electric furnace  
5,23,24 Bell-type electric furnace  
6,7 Mortising  
10,11,18 Hull-grinding  
9,12,13,33 Screw-cutting  
14,27 Circular shears  
8,16,17 Circular grinding  
19,20 Crank Press  
  Induction furnace (kVA)  
28,29 Shaping-machine  
34,38 Radial-Drilling  
31,32 Automatic lathes  
15,30 Crane with DR-40 %  
35,36,37 Horizontal milling  
  Plasma heating machine  
  Butt-welding machine with DR-25 % (kVA)  
  Electric fan  

Figure 1 – Plan of thermal workshop

Table 2 - Initial data of the workshop

 

Name of supply nodes Installed capacity, kW Mode Factors
Ки cosφ tgφ
1,2 Vertical milling   medium start 0,16 0,6 1,33
3,4,21,22,25 Chamber electric furnace   - 0,6 0,95 0,32
5,23,24 Bell-type electric furnace   - 0,6 0,95 0,32
6,7 Mortising   medium start 0,12 0,5 1,73
10,11, Hull-grinding   easy start 0,12 0,5 1,16
9,12,13,33 Screw-cutting   medium start 0,16 0,6 1,33
14,27 Circular shears   medium start 0,16 0,6 1,33
8,16,17 Circular grinding   hard start 0,25 0,65 1,16
19,20 Crank Press   medium start 0,16 0,6 1,33
  Induction furnace (kVA) 35,75 (55) - 0,25 0,65 1,16
28,29 Shaping-machine   hard start 0,25 0,65 1,16
34,38 Radial-Drilling   easy start 0,12 0,5 1,73
31,32 Automatic lathes   easy start 0,12 0,5 1,73
15,30 Crane with DR-40 % 13,91 (22) medium start 0,25 0,5 1,73
35,36,37 Horizontal milling   medium start 0,16 0,6 1,33
  Plasma heating machine   hard start 0,25 0,65 1,16
  Butt-welding machine with DR-25 % (kVA) 17,5 (50) medium start 0,25 0,7 1,02
  Electric fan   hard start 0,6 0,8 0,75

The calculation of the initial data of workshop

15, 30) Crane with DR-40 % :

26) Induction furnace (kVA) :

40) Butt-welding machine with DR-25% :

 

 

The calculation of electrical loads of workshop

 

39) Plasma heating machine:

 

Distribution board:

32) Automatic lathes

36) Horizontal milling

40) Butt-welding machine with DR-25 %

 

Total distribution board:

The exact value of m is not required, is sufficient to determine m>3 or m ≤3.

At m ≤ 3 effective number of electrical receivers is assumed equal to their actual number n: ne = n;

At m> 3 and group factor ku > 0.2 effective number of electrical receivers is defined by

from [table 3] maximum coefficient

At ,

 

Table 3 – Selecting of maximum coefficient using ne and ku

ne Use factor ku
0,1 0,15 0,2 0,3 0,4 0,5 0,6 0,7 and more
  8,00 5,33   2,67   1,6 1,33 1,14
  5,01 3,44 2,69 1,9 1,52 1,24 1,11  
  2,94 2,17 1,8 1,42 1,23 1,14 1,08  
  2,28 1,73 1,46 1,19 1,06 1,04   0,97
  1,31 1,12 1,02   0,98 0,96 0,94 0,93
6-8 1,2   0,96 0,95 0,94 0,93 0,92 0,91
9-10 1,1 0,97 0,91 0,9 0,9 0,9 0,9 0,9
10-25 0,8 0,8 0,8 0,85 0,85 0,85 0,9 0,9
25-50 0,75 0,75 0,75 0,75 0,75 0,8 0,85 0,85
More than 50 0,65 0,65 0,65 0,7 0,7 0,75 0,8 0,8

 

 

Calculation of lighting load of the workshop

 

– area of production workshop;

where kd.light.=0,85 – demand factor for active power of lighting load, , – reactive power factor.

According to the calculations we select the transformer dry and protected (protective cover) type ТСЗ-630

– load factor, which should be in the range of 0.6 - 0.85.

 


Table 4 – The calculation of loads on the workshop

 

Name of supply nodes and ER groups n Installed capacity, kW Ки cosφ tgφ Average powers nэ Км n∙Рн2 Ilong Maximum design load Id, А  
 
 
One ER ∑Р Рsh, kW Qsh, kVar Рм, kW Qм, kVar Sм, kVA  
  Plasma heating machine       0,25 0,65 1,16 22,50 26,10 1,00 4,00 8100,00 210,37 22,50 28,71 36,48 55,42  
Distribution boards  
  Automatic lathes       0,12 0,50 1,73 0,96 1,66     64,00 24,31          
  Horizontal milling       0,16 0,60 1,33 3,04 4,04     361,00 48,11          
  Butt-welding machine with DR-25 % (kVA)   17,5 17,5 0,25 0,70 1,02 4,38 4,46     306,25 37,98          
  Electric fan       0,60 0,80 0,75 18,00 13,50     900,00 56,98          
  Hull-grinding       0,12 0,50 1,16 0,72 0,84     36,00 18,23          
Total distribution boards   =30/6>3 80,5 0,34     27,10 50,60 5,37 1,00 1667,25 185,61 27,10 55,66 61,91 94,06  
Distribution busway 1  
3,4 Chamber electric furnace       0,60 0,95 0,32 42,00 13,44     2450,00 55,98          
  Bell-type electric furnace       0,60 0,95 0,32 24,00 7,68     1600,00 63,97          
6,7 Mortising       0,12 0,50 1,73 3,84 6,64     512,00 48,62          
9,12,13,33 Screw-cutting       0,16 0,60 1,33 8,32 11,07     676,00 32,92          
1,2 Vertical milling       0,16 0,60 1,33 5,76 7,66     648,00 45,58          
  Circular shears       0,16 0,60 1,33 2,72 3,62     289,00 43,05          
  Crane with DR-40 %   13,91 13,91 0,25 0,65 1,16 3,48 4,03     193,49 32,51          
8,16,17 Circular grinding       0,25 0,65 1,16 18,00 20,88     1728,00 56,10          
10,11 Hull-grinding       0,12 0,5 1,16 1,44 1,67     72,00 18,23          
  Radial-Drilling       0,12 0,5 1,73 0,84 1,45     49,00 21,27          
  Automatic lathes       0,12 0,5 1,73 0,96 1,66     64,00 24,31          
35,37 Horizontal milling       0,16 0,6 1,33 6,08 8,09     722,00 48,11          
Total distribution busway 1   =40/6>3 397,91 0,30     117,44 87,89 11,05 0,75   490,65 88,08 87,89 124,43 189,05  

 

Table 4 continuation – The calculation of loads on the workshop

distribution busway 2
21,22,25 Chamber electric furnace       0,60 0,95 0,32 63,00 20,16     3675,00 55,98        
19,20 Crank Press       0,16 0,6 1,33 4,80 6,38     450,00 37,98        
28,29 Shaping-machine       0,25 0,65 1,16 10,50 12,18     882,00 49,09        
  Crane with DR-40 %   13,91 13,91 0,25 0,5 1,73 3,48 6,02     193,49 42,27        
23,24 Bell-type electric furnace       0,60 0,95 0,32 48,00 15,36     3200,00 63,97        
  Induction furnace   35,75 35,75 0,25 0,65 1,16 8,94 10,37     1278,06 83,56        
  Circular shears       0,16 0,6 1,33 2,72 3,62     289,00 43,05        
  Radial-Drilling       0,12 0,5 1,73 0,84 1,45     49,00 21,27        
Total distribution busway 2   =40/7>3 330,66 0,43     142,28 75,54 6,30 0,85     120,93 83,09 146,73 222,93
Lighting board             17,14 5,65         17,14 5,65 17,14 26,00
Total TSS   =90/6>3 899,07 0,34     309,31 240,13 17,13 0,75     231,98 240,13 333,88 507,28

 

 


 


Table 5 - Technical data of electroreceivers

 

Name of supply nodes and ER groups Рr Ir Кcor Istart Mode α Istart Type of protection  
 
 
 
  Plasma heating machine   210,37   631,11 Hard start 1,6 394,44 circuit breaker  
Distribution boards                  
  Automatic lathes   24,31   145,86 Easy start 2,5 58,34 fuse  
  Horizontal milling   48,11   192,45 Medium start   96,23 fuse  
  Butt-welding machine with DR-25 % (kVA) 17,5 37,98   113,95 Medium start   71,22 fuse  
  Electric fan   56,98   170,93 Hard start 1,6 106,83 fuse  
  Hull-grinding   18,23   109,39 Easy start 2,5 43,76 Fuse  
Distribution busway 1                  
3,4 Chamber electric furnace   55,98   55,98 - 1,6 34,98 circuit breaker  
  Bell-type electric furnace   63,97   63,97 - 2,5 25,59 circuit breaker  
6,7 Mortising   48,62   194,48 Medium start   97,24 Fuse  
9,12,13,33 Screw-cutting   32,92   131,68 Medium start   65,84 Fuse  
1,2 Vertical milling   45,58   182,32 Medium start   91,16 Fuse  
  Circular shears   43,05   172,19 Medium start   86,10 Fuse  
  Crane with DR-40 % 13,91 32,51   130,06 Medium start   65,03 Fuse  
8,16,17 Circular grinding   56,10   168,30 Hard start 1,6 105,19 circuit breaker  
10,11 Hull-grinding   18,23   109,39 Easy start 2,5 43,76 Fuse  
  Radial-Drilling   21,27   127,62 Easy start 2,5 51,05 Fuse  
  Automatic lathes   24,31   145,86 Easy start 2,5 58,34 Fuse  
35,37 Horizontal milling   48,11   192,45 Medium start   96,23 Fuse  
distribution busway 2                  
21,22,25 Chamber electric furnace   55,98   55,98 - 1,6 34,98 circuit breaker  
19,20 Crank Press   37,98   151,93 Medium start   75,97 Fuse  
28,29 Shaping-machine   49,09   147,26 Hard start 1,6 92,04 Fuse  
  Crane with DR-40 % 13,91 42,27   169,07 Medium start   84,54 Fuse  
23,24 Bell-type electric furnace   63,97   63,97 - 2,5 25,59 circuit breaker  
  Induction furnace 35,75 83,56   250,69 Hard start 1,6 156,68 circuit breaker  
  Circular shears   43,05   172,19 Medium start   86,10 Fuse  
  Radial-Drilling   21,27   127,62 Easy start 2,5 51,05 Fuse  

 


The calculation of the technical data for power consumers and the choice of protective devices

Selecting of circuit breakers for ER №39 is made according on the following conditions:

 

Selection of the fuses for ER №32 is made according on the following conditions:

4

 

Selecting the wire to the electrical receiver №32 and cable to the load nodes is made according to the following conditions:

Where – protection current of fuse,

– protection factor,

– correcting coefficient on the conditions of installation of wiring and cables

 

Table 6 - table of correcting factor

The distance between cables in the light Correcting coefficient at the number of cables
           
    0,9 0,85 0,8 0,78 0,75
    0,92 0,87 0,84 0,82 0,81
    0,93 0,9 0,87 0,86 0,85

 

the choice of circuit breaker, cable and type of busbars

 

Distribution board:

Selecting of circuit breaker ВА 51-31-1 for distribution board is made according on the following conditions

 

For given power node we should select distribution board ПР8501-002-21УЗ

 

For given power node we select cable ААБГ 3х25

 

 

Distribution busway 1

Selecting of circuit breaker ВА 51-35 for distribution busway is made according on the following conditions

 

 

For given power node we should select distribution busway КОА0155-II-STD

 

For given power node we select cable ААБГ 3х70

 

 

Distribution busway 2

Selecting of circuit breaker ВА 51-35 for distribution busway is made according on the following conditions

 

For given power node we should select distribution busway КОА0155-II-STD

 

For given power node we select cable ААБГ 3х95

 

 

Lighting load:

Selecting of circuit breaker ВА 51-35 for lighting load is made according on the following conditions

For given power node we should select distribution busway ПР8501-002-21УЗ

 

For given power node we select cable ААБГ 3х2,5

 

 

Mains distribution busway

Selecting of circuit breaker ВА 51-39 for mainsdistribution busway is made according on the following conditions

 

For given power node we should select main busway MR 160-800

 


Table 7 – Calculation of protective devices to ER

 

Design current, А Circuit breaker Fuse Type of protection device Кprot Wires's current load Кcor Ipem.busway Mark and conductor cross-section
Ilong Istart Ir.c.b., А Tripping current, А Installation of instant trigger, А Fuse current, А Ir.fuse, А prot∙Iprot)/Кcor Istart/ Кcor
Id.tip Ir.tip Itrigger tip Ir.tip Id.fuse-link Ir.fuse-link
  210,37 631,11   210,37   788,89         ВА51-35 0,22 55,00 210,37     ААБГ-3х120
Distribution board
  24,31 145,86           58,34     НПН2 0,33 26,65 31,17 0,78   АППВ-4х10
  48,11 192,45           96,23     ПН2 0,33 42,31 61,68 0,78   АППВ-4х25
  37,98 113,95           71,22     ПН2 0,33 42,31 48,70 0,78   АППВ-4х16
  56,98 170,93           106,83     ПН2 0,33 52,88 73,05 0,78   АППВ-4х35
  18,23 109,39           43,76     НПН2 0,33 26,65 23,37 0,78   АППВ-4х4
Distribution busway 1
3,4 55,98 167,93   55,98   209,91         ВА-51-31-1 0,22 18,48 74,63 0,75   АППВ-4х35
  63,97 383,83   63,97   479,79         ВА-51-31-1 0,22 29,33 85,30 0,75   АППВ-4х50
6,7 48,62 194,48           97,24     ПН2 0,33 44,00 64,83 0,75   АППВ-4х25
9,12,13,33 32,92 131,68           65,84     ПН2 0,33 35,20 43,89 0,75   АППВ-4х16
1,2 45,58 182,32           91,16     ПН2 0,33 44,00 60,77 0,75   АППВ-4х25
  43,05 172,19           86,10     ПН2 0,33 44,00 57,40 0,75   АППВ-4х25
  32,51 130,06           65,03     ПН2 0,33 35,20 43,35 0,75   АППВ-4х16
8,16,17 56,10 168,30   56,10   210,37         ВА-51-31-1 0,22 18,48 74,80 0,75   АППВ-4х35
10,11 18,23 109,39           43,76     НПН2 0,33 27,72 24,31 0,75   АППВ-4х4
  21,27 127,62           51,05     НПН2 0,33 27,72 28,36 0,75   АППВ-4х6
  24,31 145,86           58,34     НПН2 0,33 27,72 32,41 0,75   АППВ-4х10
35,37 48,11 192,45           96,23     ПН2 0,33 44,00 64,15 0,75   АППВ-4х25
Distribution busway 2
21,22,25 55,98 167,93   55,98   209,91         ВА-51-31-1 0,22 17,33 69,97 0,8   АППВ-4х25
19,2 37,98 151,93           75,97     ПН2 0,33 41,25 47,48 0,8   АППВ-4х16
28,29 49,09 147,26           92,04     ПН2 0,33 41,25 61,36 0,8   АППВ-4х25
  42,27 169,07           84,54     ПН2 0,33 41,25 52,84 0,8   АППВ-4х25
23,24 63,97 383,83   63,97   479,79         ВА-51-31-1 0,22 22,00 79,97 0,8   АППВ-4х35
  83,56 250,69   83,56   313,36         ВА-51-31-1 0,22 27,50 104,45 0,8   АППВ-4х50
  43,05 172,19           86,10     ПН2 0,33 41,25 53,81 0,8   АППВ-4х25
  21,27 127,62           51,05     НПН2 0,33 25,99 26,59 0,8   АППВ-4х6
                                     

 

 

Table 7 – Calculation protective devices to DB, DBW, LL, DMBW

 

Design current, А Circuit breaker Type of protection device Кprot Current load of wires Кcor Ipem.busway. Mark and conductor cross-section Ilong DB Name
Ilong Istart Ir.cb, А Tripping current, А Installation of instant trigger, А prot∙Iprot)/Кcor Istart/ Кcor
Id.tip Ir.tip Itrigger tip Ir.tip
DB 94,06 -   94,06   412,44   ВА51-31-1 0,22   94,06     ААБГ-3х25   ПР8501-002-21УЗ
DBW1 189,05 -   189,05   1547,49   ВА51-35 0,22   189,05     ААБГ-3х70   КОА0155-II-STD
DBW2 222,93 -   222,93   1225,03   ВА51-33 0,22   222,93     ААБГ-3х95   КОА0155-II-STD
LL   -     31,5 26,00 94,5 ВА51-31-1 0,22 6,93       ААБГ-3х2,5   ПР8501-002-21УЗ
Total TSS 507,28 -   507,28   2475,98   ВА51-39 0,22 138,6 507,28   - -   MR 160-800

 

 


Calculation of short circuit currents

Figure 2 - design scheme

 

 

Calculation of resistance on the circuit area

Figure 3- the equivalent circuit

 

We expect resistance at TS Δ/Y0:

;

;

 

We expect resistance to the distribution busway MR:

;

;

.

 

We expect resistance circuit breaker ВА 51-39

For a circuit breaker with a rated current 630 А:

;

;

 


Area 2

We expect resistance circuit breaker ВА 51-35

For a circuit breaker with a rated current 250 А:

;

;

 

We expect the cable resistance ААБГ 3х70:

;

;

 

We expect resistance to the distribution busway KOA0155-II-STD:

;

;

.

 

Area 1

We expect resistance circuit breaker BA 51-31-1:

;

;

 

We expect the cable resistance AППВ 4х35:

;



Поделиться:




Поиск по сайту

©2015-2024 poisk-ru.ru
Все права принадлежать их авторам. Данный сайт не претендует на авторства, а предоставляет бесплатное использование.
Дата создания страницы: 2017-03-31 Нарушение авторских прав и Нарушение персональных данных


Поиск по сайту: